Check the plan against real capacity

Module 2 : Run projects faster with AI

Plan du cours

Cette leçon n'est pas encore dans votre langue, la voici donc en anglais.

Petit test

Guess first, no penalty. AI drafts a six-week plan with 600 hours of tasks for your two developers. Each has about 30 hours a week free for the project. Does it fit?

Capacity is the time people really have for your project, after meetings, support work, other projects and leave. Unless you tell it otherwise, an AI plan tends to assume everyone works full time on your project, every week, with no holidays. The plan looks complete and can't be delivered.

So check every AI plan the same way: task hours against available hours, per person, per week. Put in your team's real numbers:

Et si…

Does the plan fit? Use your team's real hours.

People on the work

2

Project hours each per week, after meetings and other work

30

Weeks in the plan

6

Task hours in the plan

600

Hours short (above zero means the plan doesn't fit)

Hours short (above zero means the plan doesn't fit): 240 hours

Une estimation à partir de vos chiffres, pas une prévision.